Mexico
Press Release

Alamos Gold announces development plan for Puerto del Aire outlining an attractive, high-return project

Bnamericas

By Alamos Gold Inc.

TORONTO, Sept. 04, 2024 (GLOBE NEWSWIRE) -- Alamos Gold Inc. (TSX:AGI; NYSE:AGI) (“Alamos” or the “Company”) today reported results of the positive internal economic study completed on its Puerto Del Aire (“PDA”) project located within the Mulatos District in Sonora, Mexico. PDA is a higher-grade underground deposit adjacent to the Mulatos open pit.

Given PDA’s attractive economics and proximity to the existing Mulatos infrastructure, the Company anticipates starting development of PDA in 2025 with first production expected mid-2027. The project is expected to nearly triple the mine life of the Mulatos District, extending production into 2035. There are excellent opportunities currently being tested that could extend the mine life further and enhance already robust economics through the significant exploration upside potential at both PDA and Cerro Pelon, as outlined earlier today.

PDA Project Highlights

  • Average annual gold production of 127,000 ounces over the first four years and 104,000 ounces over the current mine life, based on Mineral Reserves as at December 31, 2023
  • Low cost profile: total cash costs of $921 per payable ounce and mine-site all-in sustaining costs of $1,003 per payable ounce, consistent with the Company’s overall low cost structure
  • Mine life tripled to 2035: PDA mine life of eight years based on current Mineral Reserves, extending the Mulatos District mine life from 2027 to 2035
  • High-return project with significant upside potential 
    • After-tax Internal Rate of Return (“IRR”) of 46% and after-tax Net Present Value (“NPV”) (5%) of $269 million (using base case gold price assumption of $1,950 per ounce and a MXN/USD foreign exchange rate of 18:1)
    • After-tax IRR of 73% and after-tax NPV (5%) of $492 million at current gold prices of approximately $2,500 per ounce and a MXN/USD foreign exchange rate of 18:1
    • Payback of two years at the base case gold price of $1,950/oz and 1.5 years at current gold prices
  • Low initial capital to be internally funded by strong ongoing free cash flow generation at the Mulatos District 
    • Initial capital of $165 million to be spent over a two-year period starting mid-2025. Life of mine capital is expected to total $231 million including $66 million of sustaining capital
    • Low initial capital intensity of $195 per ounce produced, or $273 per ounce based on total life of mine capital
    • PDA will benefit from the use of existing crushing and mill infrastructure from Cerro Pelon and Island Gold, supporting lower initial capital and project execution risk
    • La Yaqui Grande is expected to finance the development of PDA at base case gold prices of $1,950 per ounce, following which PDA is expected to generate strong free cash flow. Through the first half of 2024, the Mulatos District generated $120 million of mine-site free cash flow
  • Lower execution risk with PDA located within existing operation 
    • Experienced team in Mexico with strong track record of building projects on schedule and within budget including La Yaqui Phase I, Cerro Pelon and La Yaqui Grande
    • PDA will represent the second underground mine developed and operated in the Mulatos District following San Carlos
    • Lower development and permitting risk with PDA located within the existing operating footprint in the Mulatos District and utilizing existing infrastructure
  • Significant exploration upside at PDA and Cerro Pelon 
    • Higher-grade mineralization continues to be extended beyond existing Mineral Reserves and Resources at PDA and the deposit remains open in multiple directions, highlighting the potential for further growth
    • Higher-grade mineralization intersected below the past producing Cerro Pelon open pit which is expected to support an initial underground Mineral Resource with the year-end Mineral Reserve and Resource update to be released in February 2025. Cerro Pelon represents upside as a potential source of additional feed to the PDA sulphide mill that could extend the higher rates of production beyond the first four years of the current mine plan

“Mulatos has been operating for nearly 20 years reflecting a long-term track record of exploration success with the discovery of multiple new deposits in the District. PDA is an extension of that success, having discovered and outlined another attractive, high-return project that we expect will extend the Mulatos District mine life to at least 2035, representing 30 years since it began producing. The development of PDA and transition to underground sulphide milling operations will open up additional opportunities for growth in the Mulatos District. Given our ongoing exploration success at PDA, and newly defined and growing higher-grade zones of mineralization at Cerro Pelon, we see excellent potential to further extend the mine life and add to already attractive economics,” said John A. McCluskey, President and Chief Executive Officer.

Puerto Del Aire Project Highlights

Life of Mine1

Production 

 

Mine life (years)

8

 

 

Total gold production (000 ounces)

848

Total payable gold production (000 ounces)

806



 Average annual gold production (000 ounces)

 

Years 1 to 4

127

Years 1 to 8

104

 

 

Total ore mined (000 tonnes)

5,375

 

 

Average gold grade mined (grams per tonne)

5.61

 

 

Average mill throughput (tonnes per day (“tpd”))

2,000

 

 

Gold recovery (%)

85%

Gold payability (%)

95%

 

 

Operating Costs 

 

Mining cost per tonne of ore mined

$88

Processing cost per tonne of ore milled

$20

G&A cost per tonne of ore milled

$20

Total site operating cost per tonne of ore milled

$120

 

 

Total operating cost per tonne of ore milled (including concentrate treatment & transportation)

$127

 

 

Total cash cost (per payable ounce)2

$921

Mine-site all-in sustaining cost (per payable ounce)2

$1,003

Capital Costs (millions) 1

 

Initial capital expenditure

$165

Sustaining capital expenditure

$66

Total capital expenditure

$231

Initial capital intensity (per ounce produced)

$195

Base Case Economic Analysis1

 

IRR (after-tax)

46%

 

 

NPV @ 0% discount rate (millions, after-tax)

$383

NPV @ 5% discount rate (millions, after-tax)

$269

 

 

Gold price assumption (per payable ounce)

$1,950

Exchange Rate (MXN/USD)

18.0

Economic Analysis at $2,500 per ounce Gold Price1

 

IRR (after-tax)

73%

 

 

NPV @ 0% discount rate (millions, after-tax)

$676

NPV @ 5% discount rate (millions, after-tax)

$492

 

 

Gold price assumption (per payable ounce)

$2,500

Exchange Rate (MXN/USD)

18.0

1 Capital spending and economic analysis (NPV and IRR) are calculated starting January 1, 2025
Total cash costs and mine-site all-in sustaining costs include silver as a by-product credit, the 0.5% government royalty on revenue, and are per payable ounce

Mineral Reserves and Resources

The PDA mine plan and economic analysis are based on Mineral Reserves as of December 31, 2023 which total 5.4 million tonnes (“Mt”), grading 5.61 grams per tonne of gold (“g/t Au”), containing 969,000 ounces of gold. Additionally, the project hosts Measured and Indicated Mineral Resources which total 2.1 Mt, grading 3.54 g/t Au, containing 240,000 ounces of gold. Only Mineral Reserves were included in the mine plan with Mineral Resources representing potential upside.

Mineral Reserves – Effective as of December 31, 2023

Classification

Tonnage (000’s)

Grade (g/t Au)

Contained oz
(000’s Au)

Proven

833

4.71

126

Probable

4,542

5.77

843

Total Proven & Probable

5,375

5.61

969

  • Mineral Reserves reported are consistent with the CIM Definition Standards for Mineral Resources and Mineral Reserves.
  • Mineral Reserves are reported to a cut-off grade of 3.0 g/t Au.
  • The cut-off grades are based on a gold price of $1,400/oz Au.
  • Metallurgical Au recovery is 85%.
  • Totals may not add up due to rounding.
  • Chris Bostwick, FAusIMM, Senior Vice President, Technical Services is the Qualified Person for the Mineral Reserve estimate. Mr. Bostwick is a Qualified Person within the meaning of Canadian Securities Administrator's National Instrument 43-101 ("NI 43-101").

Mineral Resources – Effective as of December 31, 2023

Category

Tonnage (000’s)

Grade (g/t Au)

Contained oz 
 (000’s Au)

Measured
 Indicated

326
 1,780

3.29
 3.59

35
 205

Measured & Indicated

2,106

3.54

240

Inferred

73

5.97

14

  • Mineral Resources reported are consistent with the CIM Definition Standards for Mineral Resources and Mineral Reserves.
  • The Mineral Resources are reported at an assumed gold price of US$1,600/oz.
  • Mineral Resources are not Mineral Reserves and do not have demonstrated economic viability. There is no certainty that all or any part of the Mineral Resources estimated will be converted into Mineral Reserves.
  • Contained Au ounces are in-situ and do not include metallurgical recovery losses.
  • Mineral Resources are exclusive of Mineral Reserves.
  • Totals may not add up due to rounding.
  • Marc Jutras P.Eng., Principal, Ginto Consulting Inc. is the Qualified Person for the Mineral Resource estimate. Mr. Jutras is a Qualified Person within the meaning of Canadian Securities Administrator's National Instrument 43-101 ("NI 43-101").

Economic Analysis

PDA’s estimated after-tax IRR is 46% and after-tax NPV (5%) is $269 million assuming a gold price of $1,950 per payable ounce and MXN/USD foreign exchange rate of 18:1. Assuming spot gold prices of approximately $2,500 per ounce and MXN/USD foreign exchange rate of 18:1, the after-tax IRR increases to 73% and after-tax NPV (5%) increases to $492 million.

The mine plan, operating parameters, and capital estimates incorporated in the study are based on actual operating experience, and mining contractor quotations. Capital estimates for the processing circuit are based on Class 5 estimates from the third-party engineering firm that designed the processing circuit at La Yaqui Grande.

The project economics are sensitive to metal price assumptions, foreign exchange rates, and input costs as detailed in the tables below.

Puerto Del Aire After-Tax NPV (5%) Sensitivity ($ Millions)

 

-10%

-5%

Base Case

5%

10%

Gold Price

$190

$230

$269

$309

$348

Mexican Peso

$288

$279

$269

$258

$245

Operating Costs

$305

$287

$269

$251

$233

Capital Costs

$286

$277

$269

$261

$252


 Puerto Del Aire After-Tax NPV (5%) Sensitivity to Gold Price and MXN/USD ($ Millions)

 

Mexican Peso

Gold Price
US$/oz

 

17.0

18.0

19.0

20.0

$1,750

$175

$188

$199

$209

$1,850

$216

$229

$240

$250

$1,950

$257

$269

$280

$290

$2,100

$317

$330

$341

$351

$2,300

$398

$411

$422

$432

$2,500

$480

$492

$503

$513


 Puerto Del Aire After-Tax IRR Sensitivity to Gold Price and MXN/USD (%)

 

Mexican Peso

Gold Price
US$/oz

 

17.0

18.0

19.0

20.0

$1,750

33.3%

35.6%

37.7%

39.7%

$1,850

38.8%

41.1%

43.2%

45.2%

$1,950

44.0%

46.3%

48.5%

50.5%

$2,100

51.4%

53.9%

56.1%

58.1%

$2,300

60.9%

63.4%

65.7%

67.9%

$2,500

69.9%

72.5%

74.9%

77.2%


 Project Overview

The PDA underground deposit is located adjacent to the main Mulatos pit and will be accessed via two portals located in the east wall of the Mulatos Pit (Figures 1 and 2). Underground ore mined will be processed through a flotation plant. No cyanide will be utilized with a concentrate produced for final gold recovery offsite. Tailings from onsite processing will be dry stacked.

Higher-grade sulphide mineralization was intersected at PDA more than 10 years ago. The focus at that time was on finding additional oxide, heap leachable ore such that follow up drilling at PDA did not resume until 2019. The exploration program has been extremely successful with an initial Mineral Reserve of 428,000 ounces (2.8 Mt grading 4.67 g/t Au) declared at the end of 2021. Since then, the deposit has continued to grow, more than doubling by the end of 2023 to 1.0 million ounces with grades also increasing 20% (5.4 Mt grading 5.61 g/t Au).

PDA will represent the second underground mining operation within the Mulatos District following San Carlos underground which successfully operated from 2014 to 2018. PDA will be developed by an experienced team with a strong track record of building projects on schedule and within budget including La Yaqui Phase I, Cerro Pelon, and most recently La Yaqui Grande.

Production and Mine-Site AISC Profile

Production and Mine-Site AISC Profile

Mining 

PDA will be accessed via two portals located in the east wall of the Mulatos Pit. Transverse long-hole open stoping will be the primary mining method utilized, as well as underhand drift and fill, with cemented rockfill supporting higher mining and ore recovery rates. Ore will be mined at a rate of 2,000 tonnes per day (“tpd”) over an eight-year mine life based on existing Mineral Reserves. Contract mining will be utilized over the mine life.

Initial production from PDA is expected mid-2027. Grades mined are expected to average approximately 7 g/t Au over the first four years supporting higher average annual production of 127,000 ounces over that time frame, and peak annual production of 149,000 ounces

Grades are expected to decrease to average approximately 4 g/t Au 2031 onward under the current mine plan. Ongoing exploration success at PDA and Cerro Pelon represents an upside opportunity to define additional higher-grade Mineral Reserves and Resources that could maintain higher grades and production well beyond the initial four years of the current mine plan.

Processing 

The processing circuit will include three-stage crushing, utilizing the existing Cerro Pelon crushing circuit, and two primary ball mills. One of the ball mills will come from Island Gold as the mill will be decommissioned in 2025 with ore from Island Gold to be fed through the larger Magino mill. Ore at PDA will be crushed to 80% passing (P80) ¼ inch. Following crushing, ore will be sent to the grinding circuit and then flotation circuit that includes both rougher flotation and cleaner flotation (Figures 3 and 4).

The flow sheet incorporates the following major process operations:

  • Three-stage crushing
  • Two ball mills in parallel – one to be supplied from the Island Gold mill
  • Two regrind mills – supplied from the Island Gold mill
  • Flotation circuit
  • Concentrate dewatering
  • Tailings dewatering

A concentrate will be produced with gold to be recovered off-site, eliminating the use of cyanide for on-site processing. Over the life of mine, approximately 300,000 tonnes of concentrate will be produced at average grades of 90 g/t Au. Off-site treatment, refining and transportation costs are estimated to be $130 per tonne of concentrate. Mill recoveries are expected to average 85%, of which 95% is payable.

Power to site will be supplied from the existing connection to the commercial electricity grid operated by the state-owned electric utility of Mexico, the Comisión Federal de Electricidad (“CFE”).

With the tailings dry stacked, no tailings dam will be required. Tailings will be filtered and deposited where low-grade stockpiles from Mulatos were previously located.

Operating Costs

Total cash costs are expected to average $921 per payable ounce and mine-site all-in sustaining costs $1,003 per payable ounce over the life of the operation. Total unit operating costs are expected to average $127 per tonne of ore milled, including concentrate treatment and transportation costs. This includes average mining costs of $88 per tonne of ore mined, processing costs of $20 per tonne of ore milled, and G&A costs of $20 per tonne of ore milled.

The breakdown of unit costs is summarized as follows.

Operating Costs1

 

US$/t

LOM US$M

Mining

$/t mined

$88

$473

Processing

$/t milled

$20

$117

G&A

$/t milled

$20

$117

Total On-Site Operating Costs

$/t milled

$120

$707

 

 

 

 

Concentrate Treatment & Transportation

$/t conc.

$130

$38

Total Operating Costs

$/t milled

$127

$746

 

 

 

 

Total Cash Costs2.3

$/oz

$921

 

Mine-site All-in Sustaining Costs2.3

$/oz

$1,003

 

Operating costs exclude silver by-product credit, 0.5% government royalty on revenue and working capital
Total cash costs and mine-site all-in sustaining costs include silver as a by-product credit, the 0.5% government royalty on revenue, and are per payable ounce
3 Please refer to the Cautionary Notes on non-GAAP Measures and Additional GAAP Measures

Capital Costs 

Total initial capital is estimated to be $165 million and expected to be spent over a two-year period starting mid-2025. This includes $51 million for underground development, and $109 million for the processing facility which includes a 25% contingency.

The crushing circuit that was previously utilized for Cerro Pelon will be re-located and integrated into the PDA circuit, and one primary ball mill and two regrind mills from Island Gold will be refurbished and shipped to site. The remaining life of mine capital includes $66 million of sustaining capital, predominantly for underground development.

A breakdown of the initial and total capital requirements is detailed as follows.

Capital Cost ($ millions)

 

Processing Facility1

$109

Mine Development & Fixed Assets

$56

 

 

Total Initial Capital

$165

 

 

Sustaining capital

$66

 

 

Total Capital 

$231

Includes a 25% contingency

Taxes and Royalties

Earnings at PDA are subject to the corporate tax rate of 30%, as well as the Mexican Mining Royalty (7.5% EBITDA royalty). Additionally, the project is subject to the 0.5% government royalty on revenue. The Mulatos District, including PDA is not subject to any third party royalties. Over the current mine life and using a base case gold price assumption of $1,950 per ounce, PDA is expected to pay $215 million in taxes.

Permitting

An amendment to the existing environmental impact assessment (“MIA”) will be required for PDA. The amended MIA application has been submitted with approval expected by the end of 2024. PDA is expected to be a straightforward project to permit given:

  • PDA will be an underground mine located next to the Mulatos pit, within the existing Mulatos District concessions
  • No Change of Land Use (“CUS”) permit is expected to be required with PDA located within the existing Mulatos operating footprint
  • No tailings dam will be required with dry stacked tailings
  • No use of cyanide with a concentrate to be produced and shipped off-site for treatment

Additional Upside Opportunities

Addition of a paste plant

The addition of a paste plant will be evaluated as an upside opportunity. The use of paste backfill would allow for increased mining recovery, contributing to higher life of mine production, as well as faster stope cycle times providing improved operational flexibility.

Ongoing near-mine exploration success at PDA 

Through ongoing exploration success, PDA’s Mineral Reserves base had increased to 1.0 million ounces (5.4 mt grading 5.61 g/t Au) at the end of 2023, more than doubling over the previous two years with grades also increasing 20%. This growth to the end of 2023 was incorporated into the PDA development plan.

The initial focus of the surface exploration program in 2024 has been on the GAP-Victor zones, and in the relatively untested area between the PDA zones and Gap-Victor. The program has been successful in further extending high-grade gold mineralization beyond Mineral Reserves and Resources. Given ongoing exploration success in 2024, and with the deposit open in multiple directions, there is excellent potential for further growth in higher-grade Mineral Reserves and Resources which represents upside to the project.

New highlights reported earlier today include1:

GAP-Victor Zone

  • 5.43 g/t Au over 18.05 m (23MUL278);
  • 23.60 g/t Au over 3.00 m (24MUL302);
  • 27.62 g/t Au (23.06 g/t cut) over 2.25 m (24MUL332); 
  • 12.28 g/t Au over 4.95 m (24MUL363); and
  • 5.77 g/t Au over 8.65 m (24MUL304).

PDA3 Zone

  • 3.03 g/t Au over 28.40m (24MUL347); and
  • 6.63 g/t Au over 5.50 m (24MUL365). 

PDA Extension Zone

  • 36.20 g/t Au over 0.90 m (24MUL341);
  • 3.51 g/t Au over 5.05 m (24MUL315); and
  • 4.16 g/t Au over 4.20 m (24MUL283).

1All reported composite widths are estimated true width of the mineralized zones. Drillhole composite gold grades reported as “cut” at PDA include higher grade samples which have been cut to 40 g/t Au.

Cerro Pelon and other regional targets

Cerro Pelon was an open pit operation that successfully operated between 2019 and 2021 with 127,000 ounces of gold produced at an average grade of 1.7 g/t Au. Open pit oxide ore was trucked from the Cerro Pelon pit to the existing Mulatos crushing and heap leach infrastructure, which included a dedicated Cerro Pelon crushing plant.

Between 2008 and 2017 high-grade mineralization was intersected below the Cerro Pelon pit across multiple drill holes including the following previously reported highlights from 2015 and 20162:

  • 15.35 g/t Au (14.04 g/t cut) over 25.04 m (15PEL012);
  • 9.16 g/t Au over 19.22 m (16PEL018);
  • 10.36 g/t Au over 17.40 m (15PEL020);
  • 6.95 g/t Au over 13.53 m (15PEL069); and
  • 13.47 g/t Au over 3.47 m (15PEL085).

2All reported historic composite widths are estimated true width of the mineralized zones. Drillhole composite gold grades reported as “cut” include higher grade samples which have been cut to 40 g/t Au.  

The 2024 drill program at Cerro Pelon has expanded high-grade mineralization beyond the historical drilling in multiple oxide and sulphide zones. Step-out drilling below the open pit has identified significant high-grade feeder structures that range in size from 45 to 125 metres (“m”) in width and up to 170 m vertically. New highlights reported earlier today include1:

  • 5.45 g/t Au over 27.90 m, including 31.07 g/t Au over 1.25 m (24PEL048);
  • 12.47 g/t Au (9.41 g/t cut) over 6.46 m, including 58.10 g/t Au (40.00 g/t cut) over 1.09 m (24PEL048);
  • 4.79 g/t Au over 15.82 m (24PEL071);
  • 4.46 g/t Au over 15.40 m (24PEL051);
  • 5.64 g/t Au over 12.16 m (24PEL059);
  • 5.77 g/t Au over 9.81 m (24PEL067); and
  • 4.01 g/t Au over 13.85 m (24PEL054).

1All reported composite widths are estimated true width of the mineralized zones. Drillhole composite gold grades reported as “cut” at Cerro Pelon include higher grade samples which have been cut to 40 g/t Au. 

Drilling to date indicates that more than five pipes with lateral dimensions ranging from 150 m by 100 m, to 75 m by 60 m, and vertical extents ranging between 40 m and 150 m. There is significant potential to expand the mineralization in all directions with limited drilling completed beyond the five feeders identified to date.

Cerro Pelon is located nine kilometres (“km”) by road from the planned PDA mill, similar to the distance that lower grade open pit ore from Cerro Pelon was trucked to the Mulatos circuit (Figure 5). An initial underground Mineral Resource is expected to be declared on Cerro Pelon with the 2024 year-end update which will be evaluated as a source of additional high-grade mill feed.

Under the current PDA mine plan, grades are expected to decrease from 2031 onward. Cerro Pelon represents an opportunity to mine and process higher relative grades, extending higher rates of gold production beyond the first four years of the current mine plan.

Technical Disclosure

Chris Bostwick, FAusIMM, Alamos Gold's Senior Vice President, Technical Services, has reviewed and approved the scientific and technical information contained in this news release. Mr. Bostwick is a Qualified Person within the meaning of Canadian Securities Administrator's National Instrument 43-101 ("NI 43-101").

About Alamos

Alamos is a Canadian-based intermediate gold producer with diversified production from three operating mines in North America. This includes the Young-Davidson mine and Island Gold District in northern Ontario, Canada and the Mulatos District in Sonora State, Mexico. Additionally, the Company has a significant portfolio of development stage projects, including the Phase 3+ Expansion at Island Gold, and the Lynn Lake project in Manitoba, Canada. Alamos employs more than 2,400 people and is committed to the highest standards of sustainable development. The Company’s shares are traded on the TSX and NYSE under the symbol “AGI”.

FOR FURTHER INFORMATION, PLEASE CONTACT:

Scott K. Parsons

Senior Vice President, Corporate Development & Investor Relations

(416) 368-9932 x 5439

The TSX and NYSE have not reviewed and do not accept responsibility for the adequacy or accuracy of this release.

Subscribe to the leading business intelligence platform in Latin America with different tools for Providers, Contractors, Operators, Government, Legal, Financial and Insurance industries.

Subscribe to Latin America’s most trusted business intelligence platform.