Colombia's Celsia starts La Mesa solar works
Colombia's Celsia has begun construction work on three solar parks with 60MW of combined installed capacity.
The projects are located in the municipality of La Mesa in Cesar department, the Medellín-based company said in a statement.
They will be built on 80ha of land and comprise 210,000 photovoltaic panels. Construction is expected to last 10-12 months.
Celsia transmission director Julián Cadavid said the projects, which have been the subject of three years of planning, have secured connections to Colombia's national grid.
He added that Celsia is on track to end the year with 350MW of grid-scale solar capacity.
Subscribe to the leading business intelligence platform in Latin America with different tools for Providers, Contractors, Operators, Government, Legal, Financial and Insurance industries.
News in: Electric Power (Colombia)
Ecopetrol advances plans to overhaul fossil fuel business model
Colombia's state-run company aims to replace its existing oil and gas business model with one focused on renewable energy, carbon capture and hydro...
The technology behind Colombia's clean energy revolution
ISA Intercolombia general manager Carlos Mario Caro speaks to BNamericas about the company's expansion plans and how they are being underpinned by ...
Subscribe to Latin America’s most trusted business intelligence platform.
Other projects in: Electric Power (Colombia)
Get critical information about thousands of Electric Power projects in Latin America: what stages they're in, capex, related companies, contacts and more.
- Project: Musichi wind farm
- Current stage:
- Updated:
4 days ago
- Project: EO200i wind farm (ex-wind park in Alta Guajira)
- Current stage:
- Updated:
4 days ago
- Project: Ruta del Sol photovoltaic park
- Current stage:
- Updated:
4 days ago
- Project: Andrea Jusayu wind farm (ex Cerrito wind farm)
- Current stage:
- Updated:
1 week ago
- Project: Ituango hydro (Hidroituango)
- Current stage:
- Updated:
1 week ago
- Project: Astrolabio offshore wind farm (OFW Astrolabio)
- Current stage:
- Updated:
1 week ago
- Project: Cuestecitas photovoltaic plant
- Current stage:
- Updated:
1 week ago
- Project: Termosolo 2
- Current stage:
- Updated:
1 week ago
- Project: Colectora substation and Colectora - Cuestecitas and Cuestecitas - La Loma transmission lines
- Current stage:
- Updated:
3 days ago
- Project: Hidrosantander
- Current stage:
- Updated:
1 week ago
Other companies in: Electric Power (Colombia)
Get critical information about thousands of Electric Power companies in Latin America: their projects, contacts, shareholders, related news and more.
- Company: Solano Renovables S.A.S.
- Company: Odinsa S.A.  (Odinsa)
-
Colombian construction and engineering firm Odinsa S.A., previously known as Organización de Ingeniería Internacional S.A. (Grupo Odinsa), is engaged in the structuring, promoti...
- Company: Biogas Colombia S.A.S. E.S.P.  (Biogás Colombia)
-
The description contained in this profile was taken directly from an official source and has not been edited or modified by BNamericas researchers, but may have been automatical...
- Company: Consorcio Schrader Camargo- Yellow River (CYS)  (Consorcio CYS)
-
Schrader Camargo-Yellow River Consortium (CYS) is a company formed by Schrader Camargo S.A.S. and Yellow River Co., Ltd. Colombia Branch for the execution of the Ituango Hydroel...
- Company: Comercializadora Internacional Milpa S.A.  (C.I. MILPA)
-
C.I. MILPA is a Colombian company engaged in the underground mining of coking coal and the subsequent production and commercialization of metallurgical coke. The company has res...
- Company: Solargreen S.A.S.  (Solargreen)
-
Solargreen S.A.S., the Colombian branch of the Spanish Group Solaer established in 2015 in Medellín, is aimed at the development of photovoltaic projects, including feasibility ...
- Company: Promotora de Energia de Colombia, S.A.S.  (PROMOENERCOL)
-
The description contained in this profile was taken directly from an official source and has not been edited or modified by BNamericas researchers, but may have been automatical...