Construction of the SOTE variant is 95% complete

This Petroecuador release was published using machine translation.
The General Manager of EP Petroecuador, Pablo Flores, made a technical tour of the area where the construction work for the variant of the Trans-Ecuadorian Pipeline System (SOTE) is carried out, to supervise their progress on the spot. Here he highlighted the effort of the technicians, “all the staff have done a great job and therefore we already have 95% progress. Now the work will focus on safeguarding the integrity of the pipeline, so that we have a safe operation. ”
120 technicians from EP Petroecuador and the Army Corps of Engineers participate in the repair and construction work of the new 1.75 km variant of the Trans-Ecuadorian Pipeline (SOTE), who are working hard days and in adverse conditions, since the The climate and topography of the place have been difficult for technicians.
While construction of the variant is nearing completion, quality control testing is still in place. In addition, complementary works must be carried out, which are necessary and indispensable to protect the integrity of the pipeline, in the event of possible eventualities and natural disasters.
For pipeline protection work, pipeline anchors will be installed in sectors with steep slopes and changes in pipeline direction. In addition, concrete support blocks will be placed in the sectors where there is no possibility of installing “H” frames and a pipe support bridge will be built at the Reventador river crossing with a span of 24 meters. Once all these works are completed, the SOTE pumping operation will resume.
On April 7, there was a sinkhole of approximately 70 meters, due to a sinking of land by natural factors in the San Rafael sector, the provincial border between Sucumbíos and Napo, which caused the rupture of the SOTE pipes, Poliducto Shushufindi - Quito and the Heavy Crude Pipeline (OCP).
For the construction of the variant, 160 11-meter-long, 26-inch tubes were used, material that was in stock in the warehouses of the public company. In addition, non-destructive tests were performed using ultrasound and hydrostatic tests to rule out the existence of weld failures.
It should be noted that during these tasks there have been no occupational accidents and no cases of Covid contagion 19, since high standards of personnel safety were implemented to safeguard their safety and integrity.
SOTE has a transport capacity of 360 thousand barrels of crude oil per day, from the Amazon region to the Esmeradas province.
Subscribe to the leading business intelligence platform in Latin America with different tools for Providers, Contractors, Operators, Government, Legal, Financial and Insurance industries.
News in: Oil & Gas (Ecuador)

External factors continue to affect Petroecuador production
Since August 2024 to date, Petroecuador's production in Orellana, Sucumbíos and Napo has been affected by external factors such as: equipment failu...

The challenges Ecuador faces to close oil block ITT
According to a preliminary schedule drawn up by Petroecuador, the closure and plugging of the block's 246 wells would be carried out by December 20...
Subscribe to Latin America’s most trusted business intelligence platform.
Other projects in: Oil & Gas (Ecuador)
Get critical information about thousands of Oil & Gas projects in Latin America: what stages they're in, capex, related companies, contacts and more.
- Project: Blanca-Vinita field
- Current stage:
- Updated:
7 months ago
- Project: Yuralpa field
- Current stage:
- Updated:
7 months ago
- Project: Block 61-Auca
- Current stage:
- Updated:
9 months ago
- Project: Saywa block (Intracampos II round)
- Current stage:
- Updated:
9 months ago
- Project: VHR Este block (Intracampos II round)
- Current stage:
- Updated:
9 months ago
- Project: VHR Oeste block (Intracampos II round)
- Current stage:
- Updated:
9 months ago
- Project: Block Sahino
- Current stage:
- Updated:
10 months ago
- Project: Tetete Sur block (Intracampos II round)
- Current stage:
- Updated:
1 year ago
- Project: Tamya block (Intracampos II round)
- Current stage:
- Updated:
1 year ago
- Project: Lumbaqui block (Intracampos II round)
- Current stage:
- Updated:
1 year ago
Other companies in: Oil & Gas (Ecuador)
Get critical information about thousands of Oil & Gas companies in Latin America: their projects, contacts, shareholders, related news and more.
- Company: Overtech Soluciones Técnicas S.A.  (Overtech Ecuador)
-
The description contained in this profile was taken directly from an official source and has not been edited or modified by BNamericas researchers, but may have been automatical...
- Company: Constructora Villacreces Andrade S.A.  (CVA Ecuador)
-
The description contained in this profile was taken directly from an official source and has not been edited or modified by BNamericas researchers, but may have been automatical...
- Company: Acindec
- Company: Conspeccime Cía. Ltda.  (CPM)
- Company: Pluspetrol Ecuador B.V.  (Pluspetrol Ecuador)
-
The description included in this profile was taken directly from an official source and has not been modified or edited by BNamericas’ content team. However, it may have been au...
- Company: Novacero S.A.  (Novacero)
-
The description included in this profile was taken directly from an official source and has not been modified or edited by the BNamericas’ researchers. However, it may have been...
- Company: Vepamil S.A.  (Vepamil)
-
The description included in this profile was taken directly from an official source and has not been modified or edited by the BNamericas’ researchers. However, it may have been...
- Company: Siderúrgica y Metales S.A.  (Sidermet)
-
The description included in this profile was taken directly from an official source and has not been modified or edited by BNamericas’ content team. However, it may have been au...