Costa Rica roadmap highlights need for backup thermal capacity
Costa Rica will have to maintain and increase procurement of thermal power through at least 2028, according to state power company ICE.
The outlook is part of the operator’s just-released executive summary of the 2024-40 power generation expansion plan.
The thermal capacity will mitigate the impact of weather phenomenon El Niño and help cover growing demand, until the incorporation in 2029 of 200MW from the revamp of the Moín diesel-fired plant.
A second block of thermal capacity would be required in 2033-35 to back up the partial stoppage of hydroelectric plants Arenal and Dengo for modernization work.
Read ICE begins process to contract backup power blocks for upcoming summers
[insight#260217543]
The roadmap also confirms the development of battery energy storage systems, the 53MW Fourth Cliff hydro project and the 55MW Borinquen geothermal project, along with the startup of wind and solar plants.
Read Costa Rica launches geothermal tender, extends solar project call
The executive summary is available in the Documents box in the top right corner, while the roadmap itself will be released later this year.
Subscribe to the leading business intelligence platform in Latin America with different tools for Providers, Contractors, Operators, Government, Legal, Financial and Insurance industries.
News in: Electric Power (Costa Rica)
Call for US$68mn Panama power project draws sole bidder
A roundup of sector developments in Central America.
ICE receives six electric buses donated by the People's Republic of China to Costa Rica
They will be integrated into the exploration of a business model applicable to the country
Subscribe to Latin America’s most trusted business intelligence platform.
Other projects in: Electric Power (Costa Rica)
Get critical information about thousands of Electric Power projects in Latin America: what stages they're in, capex, related companies, contacts and more.
- Project: Borinquen I geothermal plant
- Current stage:
- Updated:
2 days ago
- Project: Thermal plant in Limón
- Current stage:
- Updated:
1 month ago
- Project: Fourth Cliff hydroelectric project
- Current stage:
- Updated:
2 months ago
- Project: Tejona Wind Plant Repowering
- Current stage:
- Updated:
4 months ago
- Project: Borinquen II geothermal plant
- Current stage:
- Updated:
7 months ago
- Project: Capulín - San Pablo hydroelectric power plant
- Current stage:
- Updated:
1 year ago
- Project: Naguabo Solar Plant
- Current stage:
- Updated:
1 year ago
- Project: El Quijote wind project
- Current stage:
- Updated:
2 years ago
- Project: Reventazón Hydroelectric plant
- Current stage:
- Updated:
4 years ago
- Project: Las Pailas II geothermal complex
- Current stage:
- Updated:
5 years ago
Other companies in: Electric Power (Costa Rica)
Get critical information about thousands of Electric Power companies in Latin America: their projects, contacts, shareholders, related news and more.
- Company: Unión Fenosa Generadora Torito, S.A.
- Company: Asesorías Geotec S.A.
- Company: Inversiones Eólicas Guanacaste S.A.
-
The description included in this profile was taken directly from an AI source and has not been edited or modified by BNamericas researchers. However, it may have been automatica...
- Company: Sinohydro Bureau 11 Co. Ltd
- Company: Autoridad Reguladora de los Servicios Públicos  (Aresep)
-
Costa Rica's utility regulator Aresep has the mission to provide publicly regulated services at optimal access, cost, quality and variety. It envisions itself as a regulatory au...
- Company: INS Valores Puesto de Bolsa, S.A.  (INS Valores)
-
INS Valores Puesto de Bolsa, S.A. (INS Valores), a branch of Instituto Nacional de Seguros (INS), is a Costa Rican company established in 1997 and headquartered in San José whic...