Development of Bolivia's 100MW Laguna Colorada geothermal power project is due to pick up in the coming months as energy authorities define reference terms for the plant component.
BNamericas has learned that state power company Ende will review draft procurement documents that were prepared with the Japan International Cooperation Agency to hire the consultant that will carry out the plant's basic design.
The consultant will also accompany the bidding process, and supervise construction, installation and startup.
***
Caribbean Development Bank president Warren Smith (on the left in photo) and Neven Mimica, international cooperation and development head at the European Commission, formalized an EU grant contribution of 12mn euros (US$14mn) to the Geothermal Risk Mitigation Programme for the Eastern Caribbean.
The program will support the development of up to 60MW of geothermal capacity in Dominica, Grenada, St Kitts and Nevis, Saint Lucia, and St Vincent and the Grenadines, the bank said in a statement.
The funds will be used "to provide investment grants at the exploration phase, as well as technical assistance to support capacity-building initiatives and studies that explore opportunities for, and the feasibility of, interconnection between islands to facilitate the export of electricity by geothermal energy producers," the bank said.
Subscribe to the leading business intelligence platform in Latin America with different tools for Providers, Contractors, Operators, Government, Legal, Financial and Insurance industries.
News in: Electric Power (Bolivia)
Wind turbines for the Warnes II wind farm arrive to contribute to changing the energy matrix in Bolivia
The batch received includes key components of the Windey WD156-4500 wind turbines, each with a power of 4.5 megawatts.
Three groups vying for Bolivian green hydrogen study
The government recently inked a green hydrogen cooperation deal with Oruro department.
Subscribe to Latin America’s most trusted business intelligence platform.
Other projects in: Electric Power
Get critical information about thousands of Electric Power projects in Latin America: what stages they're in, capex, related companies, contacts and more.
- Project: Barranca Solar photovoltaic park
- Current stage:
- Updated:
2 days ago
- Project: Miguillas hydro plant
- Current stage:
- Updated:
2 days ago
- Project: Anto Ruiz III and IV hydro plants - Phase 1
- Current stage:
- Updated:
2 days ago
- Project: Combined Cycle MSW Energy Recovery Plant
- Current stage:
- Updated:
3 days ago
- Project: La Herradura I wind park
- Current stage:
- Updated:
3 days ago
- Project: Arenal Solar Plant
- Current stage:
- Updated:
3 days ago
- Project: Kairós Wind 1 wind farm (Kairós wind complex - Phase I)
- Current stage:
- Updated:
2 days ago
- Project: Pumped Storage Hydroelectric in Paute Integral Hydroelectric Complex
- Current stage:
- Updated:
3 days ago
- Project: Photovoltaic Plant Mauriti 8 (Complejo Fotovoltaico Mauriti)
- Current stage:
- Updated:
2 days ago
- Project: Mauriti 5 photovoltaic plant (Mauriti photovoltaic complex)
- Current stage:
- Updated:
2 days ago
Other companies in: Electric Power (Bolivia)
Get critical information about thousands of Electric Power companies in Latin America: their projects, contacts, shareholders, related news and more.
- Company: ISA Bolivia S.A  (ISA Bolivia)
-
ISA Bolivia S.A is a Bolivia-based power transmission company which is also engaged in the construction, operation and maintenance of power grids and the development of telecomm...
- Company: Asociación Accidental PH Ivirizu
- Company: FACER S.R.L.
- Company: Freddy Marca Cespedes
- Company: Consorcio Siemens - Ingener
- Company: REMOC S.R.L.