Google begins docking Firmina submarine cable in Brazil
Google started the deployment and docking of its Firmina submarine cable at the system’s Brazilian landing station, located in Praia Grande city.
Works began November 17 and are expected to last 10 days depending on weather conditions, according to information from the Praia Grande municipality.
“We confirm that Google service providers – responsible for installing the Firmina cable – are working in Praia Grande on cable deployment operations, as well as on the seabed and beaches,” Google said in a statement to BNamericas.
The company added:
“This work is scheduled to take place in November 2023. The Firmina submarine cable, named after Brazilian abolitionist Maria Firmina dos Reis, joins three other significant cable investments in Latin America – Monet, Tannat and Curie – which together bring more reliable connectivity to the region."
The installation will be carried out by six vessels, in addition to divers, machines and workers on land, in the sand strip, city authorities said.
Firmina will run 14,000km from Myrtle Beach (US) to Las Toninas (Argentina), with landing points in Brazil (Praia Grande) and Uruguay (Punta del Este).
As reported by BNamericas, São Paulo state environmental review agency Cetesb granted Google an environmental permit related to fuel handling at Praia Grande’s landing station in August.
"This environmental license is related to power feeding equipment (PFE) operations for our submarine cables. The license is required for the responsible handling of diesel oil used in the unit's generators," Google confirmed to BNamericas on the occasion.
The company also secured two key permits by Brazil’s environmental watchdog Ibama related to the project.
The company first obtained a preliminary environmental license for Firmina from Ibama in January, according to the watchdog's database. This license is valid through January 24, 2025, BNamericas has learned.
A second permit, the installation license, was obtained on April 26 and is valid through April 2027.
A third and fundamental permit is still pending: the operating license, which is usually valid for 10 years.
Google has an operating permit for two other submarine cables that are active in Brazil: for the Junior cable (valid through April 2028), connecting the coasts of São Paulo and Rio de Janeiro, and for Tannat (valid through May 2028), which connects Brazil, Uruguay and Argentina.
Tannat is a partnership between Telxius, Google and Uruguayan state telco Antel.
Telxius announced that it was partnering with Google for the Firmina cable, with the goal of offering redundant routes to customers of both companies’ submarine systems.
Google intends to activate Firmina in coming months.
Subscribe to the leading business intelligence platform in Latin America with different tools for Providers, Contractors, Operators, Government, Legal, Financial and Insurance industries.
News in: ICT (Argentina)
Financing watch: Startup dealmaking, IT M&As, tech training and more
A roundup of ICT financing news in Latin America.
Telecom Argentina returns to international markets with US$500mn bond issue
The issuance is part of a global program for up to US$3bn.
Subscribe to Latin America’s most trusted business intelligence platform.
Other projects in: ICT
Get critical information about thousands of ICT projects in Latin America: what stages they're in, capex, related companies, contacts and more.
- Project: Second KIO Data Center in Querétaro (KIO QRO 2) (Phase 1)
- Current stage:
- Updated:
3 months ago
- Project: Refefo fiber optic backbone network update (Stage 3)
- Current stage:
- Updated:
3 months ago
- Project: QR03 Data Center
- Current stage:
- Updated:
3 months ago
- Project: Colón data center (QRO Campus)
- Current stage:
- Updated:
3 months ago
- Project: Scala Curauma Data Center Expansion, Data Center Substation and 2x110kV SE Placilla - SE Curauma Transmission Line
- Current stage:
- Updated:
4 months ago
- Project: Norte Conectado Program (Infovia 02)
- Current stage:
- Updated:
4 months ago
- Project: Cirion Data Center (SAN2)
- Current stage:
- Updated:
4 months ago
- Project: QR02 Data Center
- Current stage:
- Updated:
4 months ago
- Project: Norte Conectado Program (Infovia 08)
- Current stage:
- Updated:
4 months ago
- Project: Norte Conectado Program (Infovia 06)
- Current stage:
- Updated:
4 months ago
Other companies in: ICT (Argentina)
Get critical information about thousands of ICT companies in Latin America: their projects, contacts, shareholders, related news and more.
- Company: Ministerio de Hacienda de la República Argentina
-
The Argentina's Ministry of Finance, headquartered in Buenos Aires, plans and monitors the financial needs of the National Treasure and helps the national budget drafting; it is...
- Company: Ente Nacional de Comunicaciones  (ENACOM)
-
Ente Nacional de Comunicaciones (Enacom) is an Argentinean autonomous and decentralized entity created in 2015 to lead the technological convergence process in Argentina and to ...
- Company: Grupo Clarín S.A.  (Grupo Clarín)
-
Argentine holding company Grupo Clarin SA is engaged in the media sector through a number of subsidiaries. Its activities are structured in four business segments namely Cable T...
- Company: Telecom Argentina USA Inc.
- Company: Unidad Ejecutora Central (UEC)
- Company: Cámara de Empresas de Tecnologías de Información de Argentina  (Cessi)
-
La Cámara de Empresas de Software y Servicios informáticos (Cessi) is the Argentinean chamber associating and representing over 800 national and foreign firms engaged in the dev...
- Company: Iplan Networks - NSS S.A.  (Iplan)
-
Iplan Networks (Iplan) is an Argentinean telecom firm founded in 1999 in Buenos Aires. Iplan is specialized in telephony, internet, cloud, and managed and professional services ...
- Company: Artes Gráficas Rioplatense S.A.(AGR)