Government begins ENEL concession termination process and demands minimum replacement for the next 24 hours
This is a machine translation of the original release issued in Spanish
PRESS RELEASE from the Ministry of Energy of Chile
August 7, 2024
The Minister of Energy, Diego Pardow, announced tonight that the Government began the administrative process of expiration of the concession in the Metropolitan Region of the distribution company ENEL.
After a meeting held at the Senapred offices in which the Undersecretary of the Interior, Manuel Monsalve, and undersecretaries from different portfolios participated, Minister Pardow pointed out that, after President Gabriel Boric requested the Ministry of Energy to review the expiration, after the Senapred meeting, the start of this process was announced. “This administrative process has several stages. Its first stage is a requirement that functions as an ultimatum, where service conditions are set that must be met within a certain period of time,” Pardow explained.
According to the authority, this ultimatum contemplates that the company comply with the new recovery plan presented, which considers the connection of 20,000 clients during the day tomorrow, Thursday. “The two previous recovery plans were not fulfilled, there cannot be a third time. This plan will be segmented into 24-hour periods and if there are not 20,000 clients connected during 24 hours tomorrow, this procedure will move to its next administrative phase, which is the adversarial phase,” added the Secretary of State.
In addition, Pardow explained that the Government has also brought charges against the distribution company CGE for violating supply replacement regulations. “ CGE has some of the communes of the Metropolitan Region affected and, in particular, by the situation in O'Higgins, where the lack of rhythm in the recovery of clients is also a reason for extreme concern,” he concluded.
Regarding the statement issued by the ENEL company during the current day, Minister Pardow asserted that he did not take into account the call made earlier by President Boric. “Our concern is how Chilean consumers are going to be asked to pay their electricity bills when the electricity distribution service has been not only incompetent, but also indolent. So how are we going to ask the clients of our country who pay their bills every day, who regularly take care of their obligations, to face this situation when companies have evidently failed to do their part in this tacit agreement that we citizens have with companies,” he expressed.
Subscribe to the leading business intelligence platform in Latin America with different tools for Providers, Contractors, Operators, Government, Legal, Financial and Insurance industries.
News in: Electric Power (Chile)
Aclara and Germany's VAC sign rare earths MOU
VAC will receive inputs projected to come from Aclara's planned US$130mn rare earths project in Chile.
Clifford Chance advises Grenergy on the financing for the first two phases of Oasis de Atacama, the largest battery...
The Clifford Chance team was led by Global Financial Markets partner José Guardo and counsel Eduardo Sánchez, and supported by associates Alejandro...
Subscribe to Latin America’s most trusted business intelligence platform.
Other projects in: Electric Power (Chile)
Get critical information about thousands of Electric Power projects in Latin America: what stages they're in, capex, related companies, contacts and more.
- Project: Halcón 2 BESS plant and transmission line
- Current stage:
- Updated:
2 weeks ago
- Project: Los Manolos photovoltaic project
- Current stage:
- Updated:
2 weeks ago
- Project: Halcón de Almagro BESS plant and transmission line
- Current stage:
- Updated:
2 weeks ago
- Project: New Transmission Line 2x220 Nueva Alto Melipilla - Nueva Casablanca - La Pólvora - Agua Santa
- Current stage:
- Updated:
2 weeks ago
- Project: Halcón 10 BESS plant and transmission line
- Current stage:
- Updated:
2 weeks ago
- Project: La Mocha Solar
- Current stage:
- Updated:
2 weeks ago
- Project: Don Álvaro Wind Farm
- Current stage:
- Updated:
2 weeks ago
- Project: Mariposa geothermal project
- Current stage:
- Updated:
2 weeks ago
- Project: Chirigües photovoltaic park
- Current stage:
- Updated:
6 days ago
- Project: Halcón 9 BESS plant and transmission line
- Current stage:
- Updated:
3 weeks ago
Other companies in: Electric Power (Chile)
Get critical information about thousands of Electric Power companies in Latin America: their projects, contacts, shareholders, related news and more.
- Company: Blue Solar Ocho SpA  (Blue Solar Ocho)
-
The description contained in this profile was taken directly from an official source and has not been edited or modified by BNamericas researchers, but may have been automatical...
- Company: Energía Renovable Violeta SPA
- Company: Consorcio Eólico S.A.  (Consorcio Eólico)
-
Consorcio Eólico S.A. (Consorcio Eólico) is a Chilean group created in 2007 by the businessman Juan Pablo Young, which is aimed at the development of renewable energy projects. ...
- Company: Áreas Verdes Austral
- Company: GR Pacama SpA  (GR Pacama)
- Company: GR Pali Aike SpA  (GR Pali Aike)
- Company: Bolero SpA
- Company: Consultora SyP Chile SpA