Jamaica highway improvement project hit by cost overruns

Jamaica’s Southern Coastal Highway Improvement Project (SCHIP) will cost an additional US$134mn, according to minister without portfolio Everald Warmington.
The project started in November 2019 with an initial cost of US$384mn but increases in construction and sewage systems costs have put it over budget.
“What this therefore means is that we will have to find additional funds to cover the cost of the higher tendered sums,” Warmington (pictured) is quoted as saying by the Jamaica Observer.
The project is being overseen by main contractor China Harbour Engineering and the original loan was agreed between the Jamaican government and China Exim Bank.
Warmington warned that more costs are foreseen as the government uses an integrated utility relocation system involving water, sewer, telecoms and other relevant infrastructure.
This will cost more but minimize disruption to customers of those utilities. Light poles and pipelines will be moved with ducts installed to allow for broadband improvements.
Jamaica’s National Works Agency (NWA) anticipates spending J$4.7bn (US$31mn) on road maintenance and repairs, disaster mitigation, bridge development and construction under the program.
The projected capital budget is estimated at J$17.4bn, sufficient to cover the current costs of SCHIP.
SCHIP involves the rehabilitation of 110km of road between Kingston and Morant Bay, and from there to Cedar Valley.
Photo: Jamaican government
Subscribe to the leading business intelligence platform in Latin America with different tools for Providers, Contractors, Operators, Government, Legal, Financial and Insurance industries.
News in: Infrastructure (China)

China’s climate-related financing gaining traction in LatAm
Beijing is now the biggest developing country contributor outside the Americas to the Caribbean Development Bank’s and IDB Invest’s climate finance...

BYD dismisses speculation on plant postponement, underscores commitment to Mexico
Like many other companies, BYD is reportedly in wait-and-see mode, given the possibility of a shift in US trade policy under a new government, acco...
Subscribe to Latin America’s most trusted business intelligence platform.
Other projects in: Infrastructure
Get critical information about thousands of Infrastructure projects in Latin America: what stages they're in, capex, related companies, contacts and more.
- Project: Pucusana Port Terminal
- Current stage:
- Updated:
5 days ago
- Project: Callao outer harbour
- Current stage:
- Updated:
5 days ago
- Project: Northern Corridor (Access to Josemaría mine)
- Current stage:
- Updated:
5 days ago
- Project: Pasamayo Serpentine - Pasamayo Variant Road Pair (Vial Network 5)
- Current stage:
- Updated:
5 days ago
- Project: Expansion and rehabilitation of Juan Pablo II highway (Heroes of the Insurrection Highway)
- Current stage:
- Updated:
6 days ago
- Project: Extension of Line 5 - Lilac of the São Paulo Metro to Jardim Ângela
- Current stage:
- Updated:
5 days ago
- Project: Juliaca - Puno highway
- Current stage:
- Updated:
6 days ago
- Project: Intermodal terminal railway - Isla La Palma
- Current stage:
- Updated:
6 days ago
- Project: Rosales New Hospital Complex
- Current stage:
- Updated:
6 days ago
- Project: Cristo Redentor Tunnel Restoration (Los Libertadores border crossing)
- Current stage:
- Updated:
6 days ago
Other companies in: Infrastructure (China)
Get critical information about thousands of Infrastructure companies in Latin America: their projects, contacts, shareholders, related news and more.
- Company: China Railway Construction Corporation Limited  (CRCC)
-
Established in 2007, China Railway Construction Corporation (CRCC) is a state-owned firm engaged in the development of infrastructure projects through four main business lines: ...
- Company: CITIC Construction Co Ltd.  (CITIC Construction)
-
Global contractor CITIC Construction Co Ltd. is the engineering and construction arm of Chinese state-owned giant CITIC Group. The EPC contractor has operations in the foreign a...
- Company: China CAMC Engineering Co., Ltd.  (CAMC Engineering)
-
China CAMC Engineering Co., Ltd is a Chinese company, subsidiary of China National Machinery Industry Corp., engaged in international project contracting, domestic and overseas ...
- Company: Wison Engineering Services Co. Ltd  (Wison Engineering)
-
Wison Engineering provides technical consultancy, procurement and construction solutions for the petrochemical and oil industries. In Latin America, it has worked on projects wi...
- Company: China Railway International Group Limited  (CRIG)
-
Construction project planner organizer, financier, designer and implementer China Railway International Group (CRIG) is the international arm of Chinese construction company Chi...
- Company: China Civil Engineering Construction Corporation  (CCECC)
-
Construction firm China Civil Engineering Construction Corporation (CCECC) provides a wide range of services for the development of civil works worldwide, including project cont...
- Company: Power Construction Corporation of China  (Powerchina)
-
Power Construction Corporation of China (PowerChina) is a state-run ECP contractor with a prominent global presence that is involved in the development of energy, transportation...
- Company: Qingjiang Group Co., Ltd
- Company: Sailun Group Co., Ltd.  (Sailun Group)
-
The description included in this profile was taken directly from an official source and has not been modified or edited by the BNamericas’ researchers. However, it may have been...