Mechanical tests begin at the Alluriquín power plant that will provide 204 MW to the National Interconnected System
The following is a machine translation of a Celec release
The review and verification of the balance of one of the three generation units of the Alluriquín power plant, which is part of the Toachi Pilatón hydroelectric complex, marks the beginning of the mechanical tests prior to the start-up of this infrastructure, which will begin the progressive delivery of energy until completing 204 MW in February 2025.
CELEC EP Hidrotoapi technical staff, together with collaborators from the contractor Tyazhmash, checked that each of the systems, instruments and components of the unit are working optimally. The verification was carried out with a nominal speed of the turbine. After the evaluation, it was determined that there were no new developments. This allows us to move on to the next process, which corresponds to the execution of the first mechanical rotation of the generation units.
On the other hand, the filling of the reservoir on the Toachi River is developing normally, within the established deadlines. As of this afternoon, a level of 940 meters above sea level (masl) was recorded, which is consolidated as a significant advance to reach the level of 965 masl, which corresponds to the minimum operating level of the reservoir of this new hydroelectric power plant.
After 14 years of waiting, following a successful political decision by President Daniel Noboa, this plant will supply electricity to the National Interconnected System in order to strengthen the generation capacity and contribute significantly to the objectives set by the Government of New Ecuador.
Subscribe to the leading business intelligence platform in Latin America with different tools for Providers, Contractors, Operators, Government, Legal, Financial and Insurance industries.
News in: Electric Power (Ecuador)
Minister (e), Roberto Luque announced that unscheduled energy rationing is ruled out
"Hydrological conditions have improved significantly in the country's main hydroelectric plants"
Hinicio and New Energy present the results of the 2024 H2LAC Index: Chile, Brazil, and Colombia lead the market
In recent years, many Latin American and Caribbean (LAC) countries have taken decisive steps to develop a hydrogen market.
Subscribe to Latin America’s most trusted business intelligence platform.
Other projects in: Electric Power (Ecuador)
Get critical information about thousands of Electric Power projects in Latin America: what stages they're in, capex, related companies, contacts and more.
- Project: Cascabel hydro-solar project
- Current stage:
- Updated:
3 months ago
- Project: Andean electrical interconnection system (SINEA)
- Current stage:
- Updated:
3 months ago
- Project: Hidroquest Hydroelectric Project
- Current stage:
- Updated:
4 months ago
- Project: Tufiño - Chiles - Cerro Negro Binational Geothermal Project
- Current stage:
- Updated:
4 months ago
- Project: Mazar floating solar park
- Current stage:
- Updated:
4 months ago
- Project: Tabacundo Solar
- Current stage:
- Updated:
4 months ago
- Project: Natural Gas Combined Cycle Block
- Current stage:
- Updated:
4 months ago
- Project: La Merced de Jondachi hydroelectric plant
- Current stage:
- Updated:
4 months ago
- Project: La Unión hydroelectric project
- Current stage:
- Updated:
4 months ago
- Project: Bajo Alto - San Idelfonso Transmission Line
- Current stage:
- Updated:
4 months ago
Other companies in: Electric Power (Ecuador)
Get critical information about thousands of Electric Power companies in Latin America: their projects, contacts, shareholders, related news and more.
- Company: Hidroabanico S.A.
- Company: Company PCA Mantenimiento Industrial S.A.  (Company PCA)
-
The description contained in this profile was taken directly from an official source and has not been edited or modified by BNamericas researchers, but may have been automatical...
- Company: SGS Ecuador
- Company: Hidronormandia S.A.  (Hidronormandia)
-
Hidronormandia S.A. is an Ecuadorian special purpose vehicle created to develop the Normandia hydro project, which involves the design, construction, operation, and maintenance ...
- Company: Efficacitas Consultora Cía
- Company: Solararomo S.A.  (Solararomo)
- Company: Ingeomática S.A.
- Company: Noboa, Peña & Torres, Abogados